Mission Timeline
As of October 2025, the mission schedule is as follows:
Main mission milestones and phases
- Ministerial Conference: End 2025
- Mission definition phase: 2026 – 2034
- Mission adoption: ~2034
- Implementation phase: 2035 – 2042
- Launch: ~2042
- Arrival at Saturn: 2053
- Tour of Saturn moons, plume sampling: 2053 - 2058
- Landing on Enceladus: 2058

Post-launch mission phases
- Launch: ~2042
- Rendezvous (RDV) phase: 0.5 - 1.5 years
- Interplanetary transfer: <10 years
- Saturn Orbit Insertion (SOI) & Perigee Raising Maneuver (PRM): 0.9 years
- Titan Gravity Assists (TGAs) & Enceladus flybys: 1.3 years
- Moon tour: 2.7 years
- Landing site reconnaissance: 1 month
- Surface operations: 1 month
- Disposal: TBD