AO-26 Timeline - XMM-Newton
XMM-Newton Twenty-sixth Announcement of Opportunity (AO-26)
Anticipated Timeline
The Twenty-sixth Announcement of Opportunity (AO-26) is not yet open
The planned key milestones for the twenty-sixth XMM-Newton "Announcement of Opportunity" have been established. Within this AO-26 a new call to submit proposals for observations to be performed with the XMM-Newton observatory will be issued.
To be prepared for this, please find below the anticipated timeline:
| The planned key milestones for AO-26 are: | ||
| Announcement of Opportunity | 19 August 2026 | |
| Due date for Proposals | 09 October 2026 (12:00 UT) | |
| Final OTAC approved programme | mid December 2026 | |
| For approved proposals only: | ||
| Start of Phase II proposal submission | 12 January 2027 | |
| Closure of Phase II proposal submission | 29 January 2027 | |
| Start of AO-26 observations | May 2027 | |